[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118100":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118100,789,1,"单选题","已知某挖土机挖土的一个工作循环需5分钟，每循环一次挖土1.5m3，工作班的延续时间为8小时，时间利用系数K=0.9，则其台班产量定额为()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10.8（立方米）\u002F台班",false,{"key":16,"text":17,"correct":14},"B","15（立方米）\u002F台班",{"key":19,"text":20,"correct":21},"C","129.6（立方米）\u002F台班",true,{"key":23,"text":24,"correct":14},"D","120（立方米）\u002F台班","2021\u002F2020教材P63页 施工机械台班产量定额=机械净工作生产率×工作班延续时间×机械利用系数=1.5×60÷5×8×0.9=129.6m3台班。 @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]