[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118090":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118090,789,1,"单选题","建设工程定额中周转材料消耗量指标中，应当用()两个指标表示。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","一次使用量和消耗量",false,{"key":16,"text":17,"correct":18},"B","一次使用量和摊销量",true,{"key":20,"text":21,"correct":14},"C","一次消耗量和计划使用量",{"key":23,"text":24,"correct":14},"D","一次消耗量和摊销量","2021\u002F2020教材P62页 定额中周转材料消耗量指标，应当用一次使用量和摊销量两个指标表示。一次使用量 是指周转材料在不重复使用时的一次使用量，供施工企业组织施工用；摊销量是指周转材 料退出使用，应分摊到每一计量单位的结构构件的周转材料消耗量，供施工企业成本核算 或投标报价使用。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]