[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118084":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118084,789,1,"单选题","编制人工定额时，应计入定额时间的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工人在工作时间内聊天时间",false,{"key":16,"text":17,"correct":14},"B","工人午饭后迟到时间",{"key":19,"text":20,"correct":14},"C","材料供应中断造成的停工时间",{"key":22,"text":23,"correct":24},"D","工作结束后的整理工作时间",true,"2021\u002F2020教材P60页 施工作业的定额时间，是在拟定基本工作时间、辅助工作时间、准备与结束时间、不可避免的中断时间，以及休息时间的基础上编制的。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]