[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118083":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118083,789,1,"单选题","某施工机械的时间定额是0.391台班\u002F100m3，与之配合的工人小组有4人，则该机械的产量定额为()m3\u002F台班。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","0.64",false,{"key":16,"text":17,"correct":14},"B","2.56",{"key":19,"text":20,"correct":14},"C","64",{"key":22,"text":23,"correct":24},"D","256",true,"2021\u002F2020教材P63页 时间定额与产量定额互为倒数，即：时间定额X产量定额=1",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]