[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118070":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118070,789,1,"单选题","某工人小组在正常的施工条件下进行砖墙的砌筑，作业过程中所消耗的时间属于定额工作时间的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工人对经检验不合格的部位重新砌筑使用的时间",false,{"key":16,"text":17,"correct":14},"B","砂浆没有按时运抵工作面而引起的停工时间",{"key":19,"text":20,"correct":21},"C","工人砌筑砖墙所消耗的时间",true,{"key":23,"text":24,"correct":14},"D","由于工地停电使砌筑施工无法进行所消耗的时间","2021\u002F2020教材P61页 时间定额，就是某种专业、某种技术等级的工人班组或个人，在合理的劳动组织和合理使用材料的条件下，完成单位合格产品所必须的工作时间，包括准备与结束时间、基本工作时间 、辅助工作时间、不可避免的中断时间及工人必需的休息时间。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]