[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118066":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118066,789,1,"单选题","关于预算定额，以下表述正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预算定额是编制概算定额的基础",true,{"key":16,"text":17,"correct":18},"B","预算定额是以扩大的分部分项工程为对象编制的",false,{"key":20,"text":21,"correct":18},"C","预算定额是概算定额的扩大与合并",{"key":23,"text":24,"correct":18},"D","预算定额中人工工日消耗量的确定不考虑人工幅度差","2021\u002F2020教材P58页 2.预算定额：预算定额是以建筑物或构筑物各个分部分项工程为对象编制的定额。预算定额是以施工定额为基础综合扩大编制的，同时也是编制概算定额的基础。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]