[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118059":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118059,789,1,"单选题","在正常的施工技术和组织条件下，完成单位合格产品所必需的人工消耗量标准，称为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","人工定额",true,{"key":16,"text":17,"correct":18},"B","材料消耗定额",false,{"key":20,"text":21,"correct":18},"C","施工机械台班使用定额",{"key":23,"text":24,"correct":18},"D","施工定额","2021\u002F2020教材P58页 人工定额，也称劳动定额，是指在正常的施工技术和组织条件下，完成单位合格产品所必需的人工消耗量标准。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]