[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118057":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118057,789,1,"单选题","已知某施工工序在合理条件下，工人在单位工日中所完成的合格产品数量为4.56m3，则该工序的人工时间定额为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.22工日",true,{"key":16,"text":17,"correct":18},"B","0.22工日\u002Fm3",false,{"key":20,"text":21,"correct":18},"C","4.56工日\u002Fm3",{"key":23,"text":24,"correct":18},"D","1.76m3","2021\u002F2020教材P61页 产量定额，就是在合理的劳动组织和合理使用材料的条件下，某种专业、某种技术等级的工人班组或个人在单位工日中所应完成的合格产品的数量。题目中的4.56m3即产量定额。时间定额是某种专业、某种技术等级工作班或个人，在合理的劳动组织和合理使用材料的条件下，完成单位合格产品所必需的工作时间。包括准备与结束时间、基本工作时间，辅助工作时间、不可避免的中断时间及工作必需的休息时间。时间定额（工日）=1\u002F每日产量，则时间定额=1\u002F产量定额=0.22工日。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]