[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118056":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118056,789,1,"单选题","能够反映施工企业生产与组织的技术水平和管理水平，直接应用于项目施工管理的定额是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","概算指标",false,{"key":16,"text":17,"correct":14},"B","概算定额",{"key":19,"text":20,"correct":14},"C","预算定额",{"key":22,"text":23,"correct":24},"D","施工定额",true,"2021\u002F2020教材P58页 施工定额是以同一性质的施工过程——工序，作为研究对象，表示生产产品数量与时间消耗综合关系编制的定额。施工定额是施工企业（建筑安装企业）组织生产和在企业内部使用的一种定额，属于企业定额的性质。施工定额直接应用于施工项目的施工管理，用来编制施工作业计划签发施工任务单、签发限额领料单，以及结算计件工资或计量奖励工资等。施工定额和施工生产结合紧密，施工定额的定额水平反映施工企业生产与组织的技术水平和管理水平。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]