[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118052":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118052,789,1,"单选题","某施工机械的产量定额为2.56(100m3\u002F台班)，与之配合的工人小组有4人，则与该机械配合的人工时间定额为( )工日\u002F100m3。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.016",false,{"key":16,"text":17,"correct":18},"B","1.563",true,{"key":20,"text":21,"correct":14},"C","10.24",{"key":23,"text":24,"correct":14},"D","0.391","2021\u002F2020教材P63页 综合时间定额=Σ各单项（工序时间定额，综合产量定额= 1\u002F综合时间定额（工日)。综合时间定额=1\u002F2.56=0.390625,综合时间定额=0.390625×4=1.563。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]