[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118041":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1118041,789,1,"单选题","斗容量1立方米正铲挖土机，挖四类土，装车，深度在2m内，小组成员两人，机械台班产量为4.76（定额单位100m3），则挖100m3的人工时间定额为( )工日。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","0.21",false,{"key":16,"text":17,"correct":14},"B","0.22",{"key":19,"text":20,"correct":14},"C","0.23",{"key":22,"text":23,"correct":24},"D","0.42",true,"2021\u002F2020教材P63页 单位产品人工时间定额（工日）=小组成员工日数总和\u002F机械台班产量 =2\u002F4.76=0.42工日",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]