[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118031":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1118031,789,1,"单选题","某施工工程人工费为80万元，材料费为140万元，施工机具使用费为40万元，企业管理费以人工费和机械费合计为计算基础，费率为18%，利润率以人工费为计算基础，费率为30%，规费30万元，综合计税系数为3.41%，则该工程的含税造价为( )万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","316",false,{"key":16,"text":17,"correct":18},"B","347",true,{"key":20,"text":21,"correct":14},"C","360",{"key":23,"text":24,"correct":14},"D","50","2021\u002F2020教材P55页 (四) 企业管理费费率。2. 以人工费和机械费合计为计算基础，则企业管理费=(80+40)×18%=21.6万。利润率以人工费为计算基础，则利润=80×30%=24万。P57：税金 = 税前工程造价 × 税率或征收率，则含税造价=(80+140+40+21.6+24+30)+(80+140+40+21.6+24+30)×3.41%=347万。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]