[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118016":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1118016,789,1,"单选题","施工成本管理应从()开始，直至项目竣工结算，保修金返还为止，贯穿于项目实施的全过程。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程投标报价",true,{"key":16,"text":17,"correct":18},"B","编制项目建议书",false,{"key":20,"text":21,"correct":18},"C","初步设计",{"key":23,"text":24,"correct":18},"D","开始施工","2021\u002F2020教材P47页 施工成本管理应从工程投标报价开始，直至项目竣工结算，保修金返还为止， 贯穿于 项目实施的全过程。 施工成本管理要在保证工期和质量要求的情况下，采取相应管理措 施， 包括组织措施、经济措施、 技术措施和合同措施，把成本控制在计划范围内，并进一 步寻求最大程度的成本节约。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]