[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118012":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118012,789,1,"单选题","根据《建筑安装工程费用项目组成》（建标[2013]44号），在工过程中，施工企业完成建设单位提出的施工图纸以外的零星项目或工作所需的费用计入（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","分部分项工程费",false,{"key":16,"text":17,"correct":14},"B","措施项目费",{"key":19,"text":20,"correct":21},"C","其他项目费",true,{"key":23,"text":24,"correct":14},"D","规费","2021\u002F2020教材P53页 三 、其他项目费。2. 计日工：计日工是指在施工过程中 ，施工企业完成建设单位提出的施工图纸以外的零星项目或工作所需的费用。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]