[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1118007":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1118007,789,1,"单选题","在计算材料单价时，依据的公式是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","材料单价=（材料原价+运杂费）×(1+运输损耗费)",false,{"key":16,"text":17,"correct":14},"B","材料单价=（材料原价+运杂费）×(1+采购保管费)",{"key":19,"text":20,"correct":21},"C","材料单价=（材料原价+运杂费）×(1+运输损耗费率)×(1+采购保管费率)",true,{"key":23,"text":24,"correct":14},"D","材料单价=材料原价+运杂费+运输损耗费","2021\u002F2020教材P54页 材料单价=（材料原价+运杂费）×(1+运输损耗率（%）)×(1+采购保管费率（%）)",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]