[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117979":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117979,789,1,"单选题","工程量清单的其他项目清单中，应包括()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","暂列金额",true,{"key":16,"text":17,"correct":18},"B","脚手架费",false,{"key":20,"text":21,"correct":18},"C","环境保护费",{"key":23,"text":24,"correct":18},"D","临时设施费","2021\u002F2020教材P53页 其他项目费由暂列金额、计日工、总承包服务费等内容构成",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]