[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117976":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117976,789,1,"单选题","在竣工验收前，对已完工程及设备进行保护所需的费用属于()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建筑安装工程措施费",true,{"key":16,"text":17,"correct":18},"B","建设单位管理费",false,{"key":20,"text":21,"correct":18},"C","建筑安装工程现场经费",{"key":23,"text":24,"correct":18},"D","建筑安装工程直接工程费","2021\u002F2020教材P52页 二 、措施项目费：5.已完工程及设备保护费：已完工程及设备保护费是指竣工验收前 ，对已完工程及设备采取的必要保护措施所发生的费用。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]