[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117973":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117973,789,1,"单选题","某施工企业对已完工程及设备的保护费用属于( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","安全文明施工费",false,{"key":16,"text":17,"correct":14},"B","财产保险费",{"key":19,"text":20,"correct":21},"C","措施项目费",true,{"key":23,"text":24,"correct":14},"D","其他项目费","2021\u002F2020教材P52页 二、措施项目费 1.安全文明施工费，2夜间施工增加费，3二次搬运费，4冬雨季施工增加费，5已完工程及设备保护费，6工程定位复测费，7特殊地区施工增加费，8大型机械设备进出场及安拆费，9脚手架工程费，",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]