[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117950":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117950,789,1,"单选题","某施工企业签订了工程施工承包合同，在项目管理目标责任书中确定了成本目标，项目经理运用动态控制原理控制施工成本的步骤中，第一步应做的工作是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","按照成本控制的要求收集施工成本的实际值",false,{"key":16,"text":17,"correct":14},"B","找出偏差，采取纠偏措施",{"key":19,"text":20,"correct":21},"C","施工成本目标的逐层分解",true,{"key":23,"text":24,"correct":14},"D","定期对施工成本的计划值和实际值进行比较","2021\u002F2020教材P29页 动态控制施工成本的步骤如下: 1、施工成本目标的逐层分解。 2、在施工过程中对施工成本目标进行动态控制和跟踪。 3、调整施工成本目标。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]