[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117948":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117948,789,1,"单选题","项目资源需求计划应当包括在施工组织设计的（）内容后。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工部署",false,{"key":16,"text":17,"correct":14},"B","施工方案",{"key":19,"text":20,"correct":21},"C","施工进度计划",true,{"key":23,"text":24,"correct":14},"D","施工平面布置","2021\u002F2020教材P26页 编制施工总进度计划后才可编制资源需求量计划（因为资源需求量计划要反映各种资源在时间上的需求）。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]