[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117947":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117947,789,1,"单选题","为了对项目目标进行动态跟踪和控制，在确定了项目目标计划值后的施工过程中，首先应做的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","调整项目目标",false,{"key":16,"text":17,"correct":14},"B","采取纠偏措施进行纠偏",{"key":19,"text":20,"correct":21},"C","收集工程进度的实际值",true,{"key":23,"text":24,"correct":14},"D","比较项目目标的实际值与计划值","2021\u002F2020教材P29页 一、运用动态控制原理控制施工进度 （二）在施工过程中对施工进度目标进行动态跟踪和控制 1.按照进度控制的要求，收集施工进度实际值。 2.定期对施工进度的计划值和实际值进行比较。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]