[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117936":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117936,789,1,"单选题","运用动态控制原理控制施工成本的步骤中，第一步应做的工作是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","按照成本控制的要求，收集施工成本的实际值",false,{"key":16,"text":17,"correct":14},"B","施工进度目标的逐层分解",{"key":19,"text":20,"correct":14},"C","定期对施工成本的计划值和实际值进行比较",{"key":22,"text":23,"correct":24},"D","施工成本目标的逐层分解",true,"2021\u002F2020教材P29页 运用动态控制原理控制施工成本步骤如下：1、施工成本目标的逐层分解；2、在施工过程中对施工成本目标进行动态跟踪和控制；3、调整施工成本目标。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]