[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117920":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117920,789,1,"单选题","某工程总承包企业与某建设单位签订了一个电站项目的EPC工程总承包合同，从风险角度分析，该项目实施风险包括()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目评估风险",false,{"key":16,"text":17,"correct":14},"B","项目决策的风险",{"key":19,"text":20,"correct":14},"C","国家财政政策与货币政策变化的风险",{"key":22,"text":23,"correct":24},"D","设计风险、施工风险、设备和其他建设物资的风险",true,"2021\u002F2020教材P39页 图表2Z101062建设工程项目的风险中有项目实施的风险，包括设计风险、施工风险、设备和其他建设物资的风险。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]