[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117903":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117903,789,1,"单选题","根据施工组织总设计编制程序，编制施工总进度计划的前一项工作是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编制资源需求量计划",false,{"key":16,"text":17,"correct":18},"B","拟定施工方案",true,{"key":20,"text":21,"correct":14},"C","确定施工的总体部署",{"key":23,"text":24,"correct":14},"D","计算主要工种工程的工程量","2021\u002F2020教材P26页 施工组织总设计的编制通常采用如下程序：(1)收集和熟悉编制施工组织总设计所需的有关资料和图纸，进行项目特点和施工条件的调查研究；(2)计算主要工种工程的工程量；(3)确定施工的总体部署；⑷拟订施工方案；(5)编制施工总进度计划；(6)编制资源需求量计划；(7)编制施工准备工作计划；(8)施工总平面图设计；(9)计算主要技术经济指标。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]