[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117899":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117899,789,1,"单选题","每一个建设工程项目有不同类型和不同用途的信息，对这些信息要进行编码。对项目结构各层中的每一项任务进行编码的依据是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","合同结构图",false,{"key":16,"text":17,"correct":14},"B","组织结构图",{"key":19,"text":20,"correct":21},"C","项目结构图",true,{"key":23,"text":24,"correct":14},"D","任务分工表","2021\u002F2020教材P12页 对项目结构的每一层的组成部分进行编码，项目结构的编码与投资控制，进度控制，质量控制，合同管理和信息管理工作的编码有紧密的联系。所以项目结构图是项目结构编码的依据。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]