[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117875":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117875,789,1,"单选题","建设项目工程总承包方项目管理工作涉及项目()的全过程。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","审批阶段",false,{"key":16,"text":17,"correct":18},"B","实施阶段",true,{"key":20,"text":21,"correct":14},"C","决策阶段",{"key":23,"text":24,"correct":14},"D","使用阶段","2021\u002F2020教材P5页 建设项目工程总承包方项目管理工作涉及项目实施阶段的全过程，即设计前的准备阶段、设计阶段、施工阶段、动用前准备阶段和保修期。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]