[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117872":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117872,789,1,"单选题","项目风险管理过程包括：1项目风险应对；2项目风险评估；3项目风险识别；4项目风险控制，其正确的管理流程是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3-2-1-4",true,{"key":16,"text":17,"correct":18},"B","3-2-4-1",false,{"key":20,"text":21,"correct":18},"C","2-3-4-1",{"key":23,"text":24,"correct":18},"D","1-3-2-4","2021\u002F2020教材P39页 施工风险管理过程包括施工全过程的风险识别、风险评估、风险响应、风险控制。 @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]