[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117869":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117869,789,1,"单选题","某施工企业在编制施工组织总设计时，已完成的工作有：收集和熟悉有关资料和图纸、调查项目特点和施工条件、计算主要工种的工程量、确定施工的总体部署和施工方案，则接下来应该进行的工作是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编制资源需用量计划",false,{"key":16,"text":17,"correct":18},"B","编制施工总进度计划",true,{"key":20,"text":21,"correct":14},"C","编制施工准备工作计划",{"key":23,"text":24,"correct":14},"D","施工总平面面设计","2021\u002F2020教材P26页 施工组织总设计的编制程序如下所示：①收集和熟悉编制施工组织总设计所需的有关资料和图纸，进行项目特点和施工条件的调查研究；②计算主要工种工程的工程量；③确定施工的总体部署；④拟定施工方案；⑤编制施工总进度计划；⑥编制资源需求量计划；⑦编制施工准备工作计划；⑧施工总平面图设计；⑨计算主要技术经济指标。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]