[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117868":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117868,789,1,"单选题","施工组织总设计包括如下工作：1.编制资源需求量计划；2.编制施工总进度计划；3.施工总平面图设计；4.拟定施工方案。其正确的工作顺序是（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1-2-3-4",false,{"key":16,"text":17,"correct":18},"B","4-2-1-3",true,{"key":20,"text":21,"correct":14},"C","1-3-2-4",{"key":23,"text":24,"correct":14},"D","4-1-2-3","2021\u002F2020教材P24页 施工组织总设计的主要内容如下：(1)建设项目的工程概况；(2)施工部署及其核心工程的施工方案；(3)全场性施工准备工作计划；(4)施工总进度计划；(5)各项资源需求量计划；(6)全场性施工总平面图设计；(7)主要技术经济指标（项目施工工期、劳动生产率、项目施工质量、项目施工成本、项目施工安全、机械化程度、预制化程度、暂设工程等）。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]