[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117867":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117867,789,1,"单选题","某建设工程项目采用施工总承包模式，其中的土方开挖工程由建设单位发包给一家专业分包商。在施工中，该土方专业分包商应该直接接受()的工作指令。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设单位",false,{"key":16,"text":17,"correct":14},"B","设计单位",{"key":19,"text":20,"correct":14},"C","监理单位",{"key":22,"text":23,"correct":24},"D","施工总承包单位",true,"2021\u002F2020教材P6页 分包施工方承担合同所规定的分包施工任务，以及相应的项目管理任务。若采用施工总承包或施工总承包管理模式，分包商（不论是一般的分包方，或由业主指定的分包方）必须接受施工总承包方或施工总承包管理方的工作指令，服从其总体的项目管理。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]