[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117862":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117862,789,1,"单选题","下列工作中,不属于施工项目目标动态控制程序中的工作是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","目标分解",false,{"key":16,"text":17,"correct":18},"B","目标计划值收集",true,{"key":20,"text":21,"correct":14},"C","目标计划值与实际值比较",{"key":23,"text":24,"correct":14},"D","采取措施纠偏","2021\u002F2020教材P27页 选项B,收集的不是计划值,而是实际值。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]