[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117861":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117861,789,1,"单选题","根据目标动态控制原理，项目目标分解之后，在实施过程中进行动态跟踪和控制的首要工作是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","确定目标控制的计划值",false,{"key":16,"text":17,"correct":14},"B","定期比较目标计划值与实际值",{"key":19,"text":20,"correct":14},"C","分析比较结果，采取纠偏措施",{"key":22,"text":23,"correct":24},"D","收集目标的实际完成值",true,"2021\u002F2020教材P27页 2. 在项目实施过程中（如设计过程中、招投标过程中和施工过程中等）对项目目标进行动态跟踪和控制：(1)收集项目目标的实际值；(2)定期（如每两周或每月）进行项目目标的计划值和实际值的比较；(3)通过项目目标的计划值和实际值的比较，如有偏差，则采取纠偏措施进行纠偏。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]