[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117860":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117860,789,1,"单选题","分部（分项）工程施工组织设计的主要内容一般不包括()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工方法的选择",false,{"key":16,"text":17,"correct":14},"B","施工机械的选择",{"key":19,"text":20,"correct":14},"C","劳动力需求量计划",{"key":22,"text":23,"correct":24},"D","主要技术经济指标",true,"2021\u002F2020教材P25页 (1)工程概况及施工特点分析；(2)施工方法和施工机械的选择；(3)分部（分项)工程的施工准备工作计划；(4)分部（分项)工程的施工进度计划；(5)各项资源需求量计划；(6)技术组织措施、质量保证措施和安全施工措施(7)作业区施工平面布置图设计。 @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]