[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117857":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117857,789,1,"单选题","按照《建设工程项目管理规范》(GB\u002FT50326-2006)，下列区域中风险等级最高的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","风险区A",true,{"key":16,"text":17,"correct":18},"B","风险区B",false,{"key":20,"text":21,"correct":18},"C","风险区C",{"key":23,"text":24,"correct":18},"D","风险区D","2021\u002F2020教材P38页 按照《建设工程项目管理规范》(GB\u002FT50326-2006)对风险等级的划分，风险区A为5等风险，风险区B为3等风险，风险区C为3等风险，风险区D为1等风险。选A。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]