[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117856":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117856,789,1,"单选题","编制施工组织总设计时，资源需求量计划应在完成( )后确定。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工准备工作计划",false,{"key":16,"text":17,"correct":14},"B","施工总平面图",{"key":19,"text":20,"correct":21},"C","施工总进度计划",true,{"key":23,"text":24,"correct":14},"D","主要技术经济指标","2021\u002F2020教材P24页 1. 施工组织总设计的内容施工组织总设计的主要内容如下： （1）建设项目的工程概况 （2）施工部署及其核心工程的施工方案 （3）全场性施工准备工作计划 （4）施工总进度计划 （5）各项资源需求量计划 （6）全场性施工总平面图设计 （7）主要技术经济指标。 @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]