[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117853":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117853,789,1,"单选题","若某事件经过风险评估，位于事件风险量区域图中的风险区 A，如下图所示则应采取适当措施降低其()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","发生概率，使它移位至风险区D",false,{"key":16,"text":17,"correct":14},"B","发生概率，使它移位风险区C",{"key":19,"text":20,"correct":14},"C","损失量，使它移位至风险区B",{"key":22,"text":23,"correct":24},"D","发生概率，使它移位至风险区B",true,"2021\u002F2020教材P37页 风险量指的是不确定的损失程度和损失发生的概率。若某个可能发生的事件其可能的损失程度和发生的概率都很大，则其风险量就很大，如下图所示。 若某事件经过风险评估，它处于风险区A，则应采取措施，降低其概率，以使它移位至风险区B；或采取措施降低其损失量，以使它移位至风险区C风险区B和C的事件则应采取措施，使其移位至风险区D。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]