[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117852":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117852,789,1,"单选题","下列各项需要编制分部（分项）工程施工组织设计内容的是（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","定向爆破工程",true,{"key":16,"text":17,"correct":18},"B","土石方工程",false,{"key":20,"text":21,"correct":18},"C","基础工程",{"key":23,"text":24,"correct":18},"D","平整场地","2021\u002F2020教材P25页 分部(分项)工程施工组织设计[也称为分部(分项)工程作业设计，或称分部(分项)工程施工设计]是针对某些特别重要的、技术复杂的，或采用新工艺、新技术施工的分部(分项)工程，如深基础、无粘结预应力混凝土、特大构件的吊装、大量土石方工程、定向爆破工程等为对象编制的，其内容具体、详细，可操作性强，是直接指导分部(分项)工程施工的依据。 @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]