[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117851":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117851,789,1,"单选题","按照《建设工程施工合同（示范文本）》的条款，下列关于更换项目经理的表述中正确的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","承包人可根据工作需要自主更换项目经理",false,{"key":16,"text":17,"correct":14},"B","发包人有权更换无权履行职责或不称职的项目经理",{"key":19,"text":20,"correct":21},"C","承包人无正当理由拒绝发包人更换项目经理要求的，应承担违约责任",true,{"key":23,"text":24,"correct":14},"D","承包人需要更换项目经理时，提前7天告知发包人和监理人","2021\u002F2020教材P31页 未经发包人书面同意，承包人不得擅自更换项目经理。发包人有权书面通知承包人更换其认为不称职的项目经理，通知中应当载明要求更换的理由。承包人需要更换项目经理的，应提前14天书面通知发包人和监理人。故选项ABD不正确。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]