[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117829":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117829,789,1,"单选题","在工程项目施工前，工程监理单位应当审查施工单位所提交的施工组织设计中的安全技术措施或者专项施工方案是否符合()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程建设设计文件",false,{"key":16,"text":17,"correct":14},"B","工程建设设计规程",{"key":19,"text":20,"correct":14},"C","工程建设施工合同",{"key":22,"text":23,"correct":24},"D","工程建设强制性标准",true,"2021\u002F2020教材P41页 工程监理单位应当审查施工组织设计中的安全技术措施或者专项施工方案是否符合工程建设强制性标准。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]