[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117824":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117824,789,1,"单选题","不属于材料和设备采购供应的建设监理工作的主要任务的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监督检查施工单位质量保证体系及安全技术措施，完善质量管理程序与制度",true,{"key":16,"text":17,"correct":18},"B","制订(或参与制订)材料和设备供应计划和相应的资金需求计划",false,{"key":20,"text":21,"correct":18},"C","通过材料和设备的质量、价格、供货期和售后服务等条件的分析和比选，协助业主确定材料和设备等物资的供应单位",{"key":23,"text":24,"correct":18},"D","起草并参与材料和设备的订货合同","2021\u002F2020教材P42页 （三）材料和设备采购供应的建设监理工作的主要任务（1）制定（或参与制定）材料和设备供应计划和相应的资金需求计划；（2）通过材料和设备的质量、价格、供货期和售后服务等条件的分析和比选，协助业主确定材料和设备等物资的供应单位；（3）起草并参与材料和设备的订货合同；（4）监督合同的实施。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]