[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117780":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117780,789,1,"单选题","下列工程施工阶段的建设监理工作中，不属于进度控制监理工作的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","监督施工单位严格按照施工合同规定的工期组织施工",false,{"key":16,"text":17,"correct":14},"B","审查施工单位提交的施工进度计划",{"key":19,"text":20,"correct":14},"C","核查施工单位对施工进度计划的调整",{"key":22,"text":23,"correct":24},"D","建立计量支付签证台账，核对工程形象进度",true,"2021\u002F2020教材P43页 建设监理工作的主要任务包括：(1)监督施工单位严格按照施工合同规定的工期组织施工；(2)审查施工单位提交的施工进度计划，核查施工单位对施工进度计划的调整；(3)建立工程进度台账，核对工程形象进度，按月、季和年度向业主报告工程执行情况、工程进度以及存在的问题。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]