[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117777":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117777,789,1,"单选题","下列选项中，属于竣工验收阶段建设监理工作主要任务的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","及时整理竣工文件和验收资料",false,{"key":16,"text":17,"correct":14},"B","提交工程竣工验收申请，编写工程质量评估报告",{"key":19,"text":20,"correct":14},"C","组织工程竣工验收，并签署竣工验收意见",{"key":22,"text":23,"correct":24},"D","编制、整理工程监理归档文件并提交给业主",true,"2021\u002F2020教材P44页 (六）竣工验收阶段建设监理工作的主要任务(1)督促和检查施工单位及时整理竣工文件和验收资料，并提出意见；(2)审查施工单位提交的竣工验收申请，编写工程质量评估报告；(3)组织工程预验收，参加业主组织的竣工验收，并签署竣工验收意见；(4)编制、整理工程监理归档文件并提交给业主。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]