[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117764":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117764,789,1,"单选题","工程所用的材料价格预计上涨的可能性属2级，且风险发生造成的损失属4级损失，则按《建设工程项目管理规范》(GB\u002FT50326-2006)规定，此种风险的等级应评为()等风险。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","2",{"key":19,"text":20,"correct":21},"C","3",true,{"key":23,"text":24,"correct":14},"D","4","2021\u002F2020教材P38页 风险等级评估如表2Z101061。 @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]