[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117752":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117752,789,1,"单选题","下列工程项目风险管理工作中，属于风险识别阶段的工作是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","分析各种风险的损失量",false,{"key":16,"text":17,"correct":14},"B","分析各种风险因素发生的概率",{"key":19,"text":20,"correct":21},"C","确定风险因素",true,{"key":23,"text":24,"correct":14},"D","对风险进行监控","2021\u002F2020教材P40页 风险识别的任务是识别施工全过程存在哪些风险，其工作程序包括：(1)收集与施工风险有关的信息；(2)确定风险因素；(3)编制施工风险识别报告。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]