[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117751":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117751,789,1,"单选题","建设工程施工过程，可能会出现暴雨、洪水，致使施工进度延误、成本增加，这种风险属于()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","经济与管理风险",false,{"key":16,"text":17,"correct":14},"B","组织风险",{"key":19,"text":20,"correct":21},"C","工程环境风险",true,{"key":23,"text":24,"correct":14},"D","技术风险","2021\u002F2020教材P39页 工程环境风险包括：(1)自然灾害；(2)岩土地质条件和水文地质条件；(3)气象条件；(4)引起火灾和爆炸的因素等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]