[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117749":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1117749,789,1,"单选题","某建设工程项目由于采用的水准仪不准，导致楼面标高和层高错误，发现问题后推倒重做，使施工进度延误、施工费用增加，该风险属于()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织风险",false,{"key":16,"text":17,"correct":18},"B","技术风险",true,{"key":20,"text":21,"correct":14},"C","工程环境风险",{"key":23,"text":24,"correct":14},"D","经济与管理风险","2021\u002F2020教材P39页 (4)技术风险，如：工程设计文件；工程施工方案；工程物资；工程机械等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]