[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117742":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1117742,789,1,"单选题","进行工程项目建设时，技术风险可能来自于（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","损失控制和安全管理人员的知识、经验和能力",false,{"key":16,"text":17,"correct":14},"B","自然灾害工程",{"key":19,"text":20,"correct":14},"C","人身安全控制计划",{"key":22,"text":23,"correct":24},"D","施工方案",true,"2021\u002F2020教材P39页 4. 技术风险，如：（1）工程设计文件；（2）工程施工方案；（3）工程物资；（4）工程机械等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]