[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117729":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117729,789,1,"单选题","下列影响建设工程项目实施的风险因素中，属于技术风险的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程勘察资料",true,{"key":16,"text":17,"correct":18},"B","气象条件",false,{"key":20,"text":21,"correct":18},"C","公用防火设施的数量",{"key":23,"text":24,"correct":18},"D","人身安全的控制计划","2021\u002F2020教材P39页 2.经济与管理风险，如：(3)现场与公用防火设施的可用性及其数量；(5)人身安全控制计划；3.工程环境风险，如：(3)气象条件；4.技术风险，如：⑴工程设计文件；(2)工程施工方案；(3)工程物资；(4)工程机械等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]