[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117715":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1117715,789,1,"单选题","施工企业与项目经理签订项目管理目标责任书的主要依据是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工企业与建设单位签订的工程承包合同",true,{"key":16,"text":17,"correct":18},"B","建设工程项目管理规范",false,{"key":20,"text":21,"correct":18},"C","施工企业投标文件",{"key":23,"text":24,"correct":18},"D","工程项目招标文件","2021\u002F2020教材P34页 施工企业与项目经理签订项目管理目标责任书的依据有： 1、项目合同文件； 2、组织的管理制度； 3、项目管理规划大纲； 4、组织的经营方针和目标； 5、项目特点和实施条件与环境；",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]