[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1117714":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1117714,789,1,"单选题","项目经理有权采取必要的措施保证与工程有关的人身、财产和工程的安全，但应在()小时内向发包人代表和总监理工程师提交书面报告。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","12",false,{"key":16,"text":17,"correct":14},"B","24",{"key":19,"text":20,"correct":21},"C","48",true,{"key":23,"text":24,"correct":14},"D","8","2021\u002F2020教材P31页 项目经理按合同约定组织工程实施。在紧急情况下为确保施工安全和人员安全，在无法与发包人代表和总监理工程师及时取得联系时，项目经理有权采取必要的措施保证与工程有关的人身、财产和工程的安全，但应在48小时内向发包人代表和总监理工程师提交书面报告。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]